Gas
Gas Trenching - Day One
Prerequisites for Gas:
-
Not really a pre-req, but the heater must be present (if a natural-gas
powered heater will be used for heating spa/pool) so that they can do the
hookup prior to completing job.
Natural gas is not needed for a pool unless you plan to heat it with a natural gas-powered
heater. Or, you may want to put in a spa and heat it the same way . In my case, I
also wanted to put in a gas-powered BBQ, Beehive Fireplace, and a Fire Pit Ring as 
well. Gas runs are expensive here in AZ - about
$9.00-$10.00 / foot for the
main line from your gas meter to the equipment pad. Electrical runs by
comparison are typically less than half that cost. I found out quickly
that when gas in involved, it will pretty much dictate where the equipment is
going to be placed - unless of course you've got money to burn. If money
wasn't an object, I would have located the equipment on the right side of the
house where it would have been hidden better and would have been on the side of
the house that gets no traffic (no gate on that side).
CONTINUED BELOW
ADVERTISEMENT
It would have been
located closer to the electrical service panel but the gas run would have been
twice the length. Unfortunately, because of the cost issue, I had to locate it
on the side of the house which is closer to the gas meter. That happens to
be the side that gets all the
traffic and is much more narrow. Go figure. There wasn't a lot I
could do about it.
Most gas subs I talked to have what they call a base price which includes a
standard amount of gas line. This base price is right around $500.
It typically includes:
-
City Permit (if applicable for your AZ city) for the gas work
-
25 ft of gas line (typically they run 1-1/2"
Polyethylene/Scotchcoat line) from your gas meter to equipment
-
Includes hookup to the gas meter and heater and all material
and labor
Additional charges will be incurred for:
-
Any additional 1-1/2" Polyethylene line past the first
25 ft.
-
Any hand digging, hard digging, or under sidewalk tunneling
that is necessary
-
Additional line for other devices (typically this would be
3/4" PE line tapped off the 1-1/2" PE main) and the associated
fittings, valves, risors, "T"s, rings, etc. necessary
-
Any PVC sleeving that would go under decking. This
sleeving houses the gas line under the deck. The idea is that if there
ever were a leak in the PE line, the gas would be forced to follow the PVC
sleeving until it came up out of the surface rather than saturating under
the ground.
The gas work requires a separate permit by the
City of Chandler. Fortunately, I didn't have to deal with it. Most
gas subs will include it as a part of the base price. It usually takes a
few days for them to get the permit. Its done by the same group that gave
me my permit for the pool. Anything above and beyond the 25ft of included
gas line will be extra. And this is where it gets expensive.
Anything over the first 25ft of line (for the main) will be charged at $9-$10
per foot. This is typically 1-1/2" - 2" PE line depending on the
length of your gas run and the amount of BTU's you will be burning. You
can see the 1-1/2" PE line in the picture to the right. Also, if
you are going to add a gas BBQ/Fireplace/Kiva/Tiki Torches/Firepits or any other
item that requires gas, what they do typically is tap off your gas hookup at
your equipment and run smaller line (typically 3/4" to 1" PE line
depending on how many BTUs your device is capable of and how long the run is) to
your various hookups. Each item hookup also requires a Tee and Risor and
is terminated with a key valve. The key valve is what will be visible on
the surface of the Fireplace or Firepit. Its a valve that is turned on or
off with a key. You can see a picture of it to the left. When I called Barbeques Galore here in Chandler, they told
me that even their biggest BBQ units only required 1/2" gas line. When
I checked with the subs, no one did anything smaller than 3/4" PE. I
guess they do that as a margin of safety. The only other thing they charge
for is if they have to do hard digs (through a lot of rocks, or under a
sidewalk, or anything that requires hand digging). For that they charge by
the foot. That goes anywhere from $2 - $8 per foot. I also found out
that most gas subs will disavow all responsibility for any broken landscaping
piping that they break. Others will not as long as they are notified of
them upfront.
One other thing I found out - gas subs really do not have to
come in at the point I listed in the Table of Contents. No other
sub really depends on them until decking is poured, and that's only if you are
planning to run gas lines through the concrete decking to some BBQ unit or other
gas-powered device. The gas subs for sure need the heater to be present
so that they can do the hookup, which means the plumbers have to set down the
equipment before they can FINISH their work, but
they can come in as late as just before the decking concrete is poured.
However, if you ask most gas subs, they would rather come in earlier rather than
later. The reason for this is that by city code, they are required to bury
their lines the deepest (18") and they would stand a higher chance of
breaking other lines - PVC or electrical - since those lines are buried at a
shallower depth (6").
I went with AZ Gas Piping as my gas sub. Ray is a great
guy. He was probably the most engaging and helpful sub that I dealt with
during my pool building experience. He sat and talked with me for about an hour one night as he came to
do my bid. He made sure I understood exactly what he was going to do, even
though I didn't really need to know all the details. But I'm glad he
did. I the wiser for it now and understand gas work much better now.
He's only been in business about a year or two and has done about 50 jobs to
date. However, he has never gotten a complaint and has never had to go
back to fix anything. He's got a clean record at the ROC and just an
all-around friendly guy. He also gave me the names of tons of other subs
who he said he would stake his reputation on. He even invited me over to his house to check out how he did his
pool / spa / backyard / deck to get some ideas.
The gas line installation process has a lot of steps but is
pretty straightforward.
-
An 18" deep trench is dug (thats code in the City of Chandler - YMMV)
from the gas meter to the back of the equipment pad where the gas-powered
heater sits. Additional trenching is done from that spot to other areas
where gas will be needed for other devices. In my case, that would
also include a BBQ, a beehive fireplace, and a fire ring.
-
The main Polyethylene line is laid from the gas meter all
the way back to the heater where a riser and "T" are
installed. From there, 3/4" Polyethylene is tapped from the
1-1/2" main and makes it way back to each of the other gas devices
where riser's and T's are installed for each. Where any PE line will
be under decking, the line will be sleeved with a PVC pipe that needs to be
twice the size of the PE pipe (so if 3/4" PE is used, PVC must be at
least 1-1/2" - don't know about the schedule though) for safety
reasons. The pipe is not actually hooked up to the gas meter at this
point. It is left stubbed up with a metal cap until after the
inspection is done. The homeowner is responsible for calling the gas
company to have them come out to install a new gas meter for the additional
gas run. This is done typically after final inspection but before the
interior sub comes through. The heater must be hooked up and
functional prior to start-up because that's when all the equipment gets
tested out.
-
By code, #18 AWG tracer wire must be laid down on top of all
the gas piping that is put into the ground. This tracer wire is used
by Bluestake and Gas officials to locate where gas pipes are run. I
don't know what they use, but apparently they have some kind of detection
device that can sense metal wire down 18" deep in the ground.
-
The entire run of piping is pressurized to 65psi with an air
compressor. The City of Chandler requires at least 60psi for 30
minutes when they come to do the inspection. This inspection is done
independently of the two pool inspections. The pipes are pressured to
at least 65psi to account for fluctuations in the pipe pressure due to
temperature variations throughout the day.
-
The trench that the pipe is laid in is left open and bare
for the inspection.
-
The City Inspector comes through and makes sure everything
is done according to code. If it is, the site will be
"Green-tagged" which means that it passed. If not, it will
be "Red-tagged" which means there are problems and that Ray has to
come back out to fix the problem before the next inspection.
-
Once the job has been "Green-tagged" the trench is
filled in.
-
After the forms for the decking goes in, Ray comes back to
set the key ring/valve for the fire ring. He does this right after the
forms go up but before the concrete is poured so that he knows at what
elevation/height to set the key ring/valve so that it will be flush with the deck
surface. At this time he also hooks up the gas heater.
-
After decking is done and after final inspection, Ray will
finish up the key valve so that its flush with the top of the deck.
-
After the BBQ and Fireplace go in, the BBQ will be hooked up
to
the gas line and the key valve will be set on the Fireplace.
-
After final inspection, but before interior, the homeowner
(that's me) needs to call up the gas company to hook up the new meter.
Ray would then come back and tap his main line into this meter and turn
everything on. He would then perform final tests to make sure
everything is in good working order.
Friday, September 20, 2002 - 8:14AM

Ray showed up bright and early on Friday morning to start the job. For the
work, Ray brought two helpers with him. Their job for the day was to do all
the trenching. Ray would be marking the areas where the key valves and the
gas lines were going to go and would be working the trenching machine for the
gas runs. Ray's assistants started out by clearing out a tunnel underneath
my existing sidewalk to go from the gas meter to the other side where the main
run would start towards the back of the house. For that part, there was
nothing better than just some shovels and some hard work. You
can see the gas meter in the first picture to the left. Its in the upper
left corner of the picture against the wall. They needed to tunnel under
the sidewalk to the other side where the open dirt path to the back runs.
I was surprised that they didn't need to use a jet water hose to blast through
there. The guys were very efficient. Once they got under the
sidewalk, they had to tunnel under the fence footer. The footer seemed
like it was close to 2ft below grade. It was just a solid nuisance and
they really had to work to get under that thing. You can see in the middle
and right pictures the hole they had to dig to get through. I took a
picture of the footer tunnel as I stood directly above it and man, it was
cavernous.
 Ray's
first task was to determine where the riser's and T's were going to be
located. There was quite a bit of reworking of the whole deck area and
where the BBQ and Beehive Fireplace (FP) were to be located from the original
plan. The original plan called for
the FP and BBQ units to be sitting on the deck. I had not realized how
small the deck area was going to be with a 9 ft radius. After going
through some discussions with Ray (and him graciously letting me come over to
his residence to see how he laid out his backyard decking), I decided that for
space considerations I would move the BBQ and FP off the deck and against the
wall and corner of the property. After seeing how much space a standard
patio table with four chairs takes up on the deck, I really didn't have a
choice. The picture below shows the new locations for the BBQ and
Beehive FP. You can see that they are now up against the property line to
conserve deck space. During discussions with Ray, I also decided to throw
in a gas-powered Fire Pit. I was over at Ray's place and saw his Fire Pit and thought it was the coolest thing. He said he could do that
for me for any extra $250. That would include running the 3/4" PE gas
line and setting the fire ring and the key valve. Deal. The hole for
the Fire Pit would be 30" in diameter. An fire ring 18" in
diameter would be placed into the hole. These
changes/additions forced Ray to have to go back to the City of Chandler and make
an addendum to the plan that he had submitted weeks earlier. Fortunately,
he was able to get away with paying only an additional $25 for a new plan review
fee. I didn't want to have to start the whole process over and have to pay
the permit fee as well. 
The
red lines show where the gas pipes are going to be placed in the ground.
Again, all the pipes are required by code to be 18" below grade. The
runs will include:
-
The main run from the gas meter to the heater - it will be
1-1/2" PE
-
The additional device runs from the heater to the BBQ, FP, and
Fire Pit / Fire Ring - they each will be 3/4" PE
Ray started off by measuring the distance from the wall the
Beehive Fireplace valve was going to be located. I didn't have the exact
plans for the FP at the time, so we had to make an educated guess as to the best
place to put it. We decided to place the valve close to the wall (so that
it would be hidden inside the FP) about 5'4" from the back wall. You
can see Ray measuring off the distance from the back wall and spraying a bright
orange dot on the ground where the riser and T will come out.
Next was the BBQ. In the middle picture below, you can see Ray
drawing in the line that represents the right edge of the BBQ. Just below
the tape measure in the same picture, he drew in the thickness of the masonry
block (8") to make sure we cleared that. In the last picture to the
right, you can see where he placed the valve location. Its the bright
orange spot just in front of the shovel's nose. Its marked about 12 inches
from the wall and about 18" away from the right edge of the BBQ.
Last, but not least - the fire ring. Ray first marked
off the center of the deck with a small "+" sign, then drew a circle
around it to represent the size of the outer hole and a small inner circle (part
of it anyway) to show where the fire ring was going to sit in relation to the
bigger hole. The hole in the ground would have a 30" diameter and the
fire ring itself would be a 18" diameter ring. By code, the key valve
for the fire ring had to be no more than 3 ft away from the edge of the
ring. In the picture to the right, you can see Ray marking off a bright
orange spot for where he wanted to locate the key valve, then making sure it was
within the 3 ft requirement.
After all the markings were made, Ray took the ditch witch (or is it a trench wench?) trenching machine
and started going after it. That thing really hummed. He started
first at the Beehive Fireplace and cut a little 4 ft trench for it near the back
corner of the lot.

After finishing that, he continued to work the other two runs - one for the BBQ
and one for the fire ring. You can see the finished runs in the picture in
the middle below. The picture to the right show the addition little jog
over to the area for the fire ring.
 After
finishing that side of it, Ray had to moved over to the equipment area for the
main run. To connect the two sides, Ray had to burrow underneath the
mountain of PVC plumbing and electrical conduit to get through to the other
side. You can see in the picture below to the left, the tunnel that he had
to create to get through. From there, he started to work his way from the
equipment all the way to the front of the house. You can see him starting
to plow through to the front in the picture to the right.
I
had to run out for a lunch meeting, but when I came back, Ray and his crew had
already left. My wife told me that Ray said that they had finished up the
trenching and would be back on Monday to lay the pipe. She also mentioned
that the electrical guys were in for about an hour to do something, but she
wasn't sure what. They had asked her some questions about the job, but
since she couldn't answer the questions, they left for lunch. When I went
back outside to survey the work, this is what I saw:


And
thats about it for the first day. It took them about 7-8 hours, but at the
end of it, they finished completely trenching 18" below grade from the gas
meter at the front of the house, all the way to the equipment and to the deck
area for the other devices. They left just after 3PM on Friday. Ray
said that they would be back on Monday morning to lay the pipes and to finish
the rest of the work.
<-
Electrical 3rd Day - Back
Next - Gas Pipes - 2nd Day ->
|